Roofs are constantly exposed to the elements and harsh conditions. Therefore, it is inevitable that they will get weak over time and demand a repair or replacement. As a homeowner, repairing or replacing your roof is not a walk in the park. One of the common concerns you have about projects like this is how long the roof repair or replacement will take.
In this article, we will address this concern by discussing the different types of roof repairs and the numerous factors determining how long it will take to complete them. Reading this will help you make informed decisions when planning for the process.
Roof Repairs Vs. Replacements
The kind of service you need for your roofing project will determine how long it will take to complete. Hence, factoring in each service’s timeline is essential for making plans and setting a feasible timeline for your project. You might detect a problem with your roof and assume it is a problem that needs a quick repair. You may be wrong and end up needing a complex fix or a total replacement that will take more time to complete.
Hence, we recommend getting a reputable roofing contractor to inspect your home and determine if it needs a roof repair or replacement. They will thoroughly inspect your roof to determine the problem, the possible solutions, and the best service to solve it. The following factors will influence your decisions: A complete roof replacement, a layover, and a fix.
A Complete Roof Replacement
As a homeowner, a total roof replacement means you have to plan an expansive project to fit your schedule. The major components that make a roof include decking, flashing, underlayment, original structure, and a layer of tiles or shingles. Installing these layers will consume time. However, how much time it takes will depend on the type of tiles or shingles you choose. Generally, installing a roof can take between two and fourteen days.
A Layover Roof
In the case that your roof is in good health in terms of security and all you need is a curb appeal elevation, a layover is what you need. A layover involves laying new shingles over the existing ones. Tearing your old roof off won’t be necessary for your roofing contractor as it would for a roof repair or replacement. What they will do is place a new layer of shingles or tiles on the old one. A layover procedure usually takes a day to complete.
This approach is ideal if you want to elevate your roof’s look. However, this service has a drawback: You can’t do more than two layers. So, say the homeowner before you already did a layover roof, you won’t be able to choose this option. In addition, layover roofs don’t work for all types of tiles. You can lay traditional tiles over traditional tiles. However, if your roof shingles style differs, you must tear them off and start afresh.
Roof Repairs
For people who live in areas that experience adverse weather conditions like wind and storm, roof repair is a common practice. Your roof may have water damage, loose shingles, or hail damage, which will call for repair.
Missing or Damaged Shingles Replacement
Many factors can make roof shingles loose. They include wind, poor installation, hail, and rain. One or more of these factors can be responsible for loose shingles. Fixing loose shingles will take a few hours, depending on the number of loose shingles you have to repair. If the number of loose shingles is 30% or more, you might need a roof replacement instead of a repair. It is a more cost-effective option.
Leaks and Water Damage
Water damage is a typical roof issue that no one should experience. It results from leaks, which give water access to a roof system and a home’s interior. Even after fixing the leak, the damage may have been done by water, leaving you to deal with wood rot. When this happens, a complete roof replacement is the way forward.
Before things get out of hand, you have to curb leaks as soon as you detect them. Start by identifying and locating the source. This part of the process takes more time than the actual repair, which could take about 30 minutes or less. Collaborating with your roofer by giving them all the necessary details will make the process faster.
Repairing and Replacing Chimney Flashing
Repairing or replacing a damaged or cracked chimney flashing is more complicated than fixing loose shingles. To restore damaged chimney flashing, a roofer must remove the shingles surrounding the chimney, the ruined flashing, and, in some cases, some chimney siding. Due to its complexity, it will take a day to complete.
Roof Replacement Materials: Shingles, Waterproofing, Ventilation, and More
There are about 18 various types of shingles. Did you know that? Hence, if you have a schedule for your roofing project’s duration, consider the kind of tile and shingle you select.
Below are four of the most common roof shingles and tiles and an estimated duration it takes to complete a project using them:
- Asphalt shingles: 1-2 days
- Wooden shingles: 3-4 days
- Slate shingles: 6-7 days
- Concrete shingles: 8-9 days
Although there are some other roofing options, including wood shake, copper shingles, and solar shingles, they aren’t so common. In addition, they are more complicated to work with. For a homeowner with a tight deadline, we recommend using asphalt shingles for your project, as they don’t take as much time as others. However, if you have the time and care about aesthetics as much as functionality, you can go with any option that matches your preference.
Square Footage
The size of your roof also impacts how long it will take to repair or replace it. Although this doesn’t significantly affect many people’s decisions, it’s essential that you factor it in when you have a deadline to meet.
A roof size of about 1600–3000 square feet typically takes 1-2 days to complete. The bigger the roof, the more time you need for a repair or replacement. This difference might not be significant to some, while for others, it could ruin their plans or make them.
Roof Complexity
Steep roofs are more complex to deal with. Hence, the steeper the roof, the more time it takes to work on it. Working on a steep roof requires extra safety measures. In addition, you may need added scaffolding, ladders, and harnesses to finish the installation without any trouble. It may take you a day to complete a roof installation on a steep roof.
You cannot avoid taking all the necessary safety measures, as following them is essential for your safety, workers, and property. Therefore, skipping the required safety measures is not an option if you have a steep roof and are working with a tight deadline for your roof repair or replacement. You just have to deal with it so you don’t end up being sorry.
Weather and Roofing Conditions
Sometimes, you and your contractor try your best to avoid delays in your roof project. However, your best isn’t just enough, thanks to circumstances beyond your control. Such circumstances include roof and weather conditions, which interfere with installation.
For instance, a roofing contractor cannot proceed with the roof repair or replacement during rain or snowfall, as water will get into the roof and building, leading to water damage. When water comes into contact with the roofing structure, such as the decking, you can’t proceed with the installation, as building codes do not support it. Aside from that, adherence to the roof surface will be a challenge for roofing materials. Hence, all roofing activities should be put on hold until it stops raining and snowing and the conditions are ideal.
Conclusion
It can be time-consuming and stressful to schedule a roof repair or replacement. However, knowing the duration of a repair or installation job can make a huge difference and ease the stress.
Generally, the average time to complete installation is 1-2 days. However, various factors will determine how long your roofing project will take. Coming this far into this article, you must already know this. The type of roofing material, steepness, weather and roofing conditions, and square footage are things you should consider when creating a deadline for your project. So, to be safe, don’t hesitate to speak with your roofing contractor and let them guide you with the correct information.
Frequently Asked Questions
How long does a roof last before replacement?
The expected lifespan of a roof largely depends on factors like the quality of roofing material and skill, location, and durability, among others. However, roofing materials have an average lifespan of 25 to 50 years.
How many days does it take to complete a roof repair or replacement?
There’s no direct answer to this, as the answer varies depending on factors like the roofing material, steepness, weather conditions, and roof size. However, it could range from a couple of hours to three days.